Outside, the trench for the telephone cable was completed; the trench for the water pipe was also completed up to the edge of the property. We only have to wait for the Northern Ireland Housing Executive to get its act together so that we can connect to the water mains (watch this space - it may take months)!
The trench for the electricity has also been started (see pic).
At the back of the house, the steps are finished, the patio wall is complete and much of the patio base has been filled.
Indoors, the plaster board work is complete (apart from the areas where the flashing needs to be adjusted. Also, the plasterers have started upstairs and the scratch coat is finished in the boys' rooms.